CertainTeed Process Piping and Equipment Installation

Installation of process equipment and piping for a state of the art asphalt roofing shingle plant

  • Zero Recordable Accidents
  • Receive the Outstanding Mechanical Installation Award from the MCA of Eastern Missouri.
  • We set over 600,000 pounds of process equipment
  • Installed over 75,000 feet of process piping, tubing and tracing
  • Over 74,000 man hours
  • Over 14,000 man hours of shop fabrication to complete 3750 pipe spools.
  • 12 month from start to substantial completion
  • Utilized cranes ranging from 8 to 650 tons of capacity
  • Installed over 8000 feet of steam tracing
  • Installed over 7000 feet of hot oil tracing